Earth Grid Design / Step and Touch
Client: South 32 Groote Eylandt
Cell was engaged to verify the step and touch voltage for the site power station generator replacement project. We supplied equipment and labour to complete the tasks and coordinate activities with the facility. A detailed report was completed with GA drawings showing step and touch results across the site based on our injection testing. Cell also completed a detailed model of the site to predict results and design parameters for the new equipment. Cell used its own internal off-frequency injection test unit to complete the tasks. We have units located in Darwin and Mackay.
Time Frame:
Completed in 2024
Approx. Value:
$12,000